Construction on the Counter Improvised Explosive Device

Similar

Construction on the Counter Improvised Explosive Device

description

Summary

Construction on the Counter Improvised Explosive Device Village at the Wyoming National Guard's Camp Guernsey Joint Training Center, in Guernsey, Wyo., continues, Oct. 5. The village is being constructed at a cost of $1.5 million and will include an underground tunnel system, a prison complex, hidden passageways, false walls, pop-up targets, and adjacent counter IED walking paths and roadways. The project is on track to be fully operational by the spring of 2011.